Precautions for installation of solar street lamp foundation

With the continuous development of solar energy technology, solar street lamp products are becoming more and more popular. Solar street lamps are installed in many places. However, because many consumers have little contact with solar street lamps, they know less about the installation of solar street lamps. Now let’s take a look at the precautions for installing the solar street lamp foundation for your reference.

1. The pit shall be excavated along the road in strict accordance with the size of the solar street lamp foundation drawing (the construction size shall be determined by the construction personnel);

Solar street lamp installation

2. In the foundation, the upper surface of the buried ground cage must be horizontal (measured and tested with a level gauge), and the anchor bolts in the ground cage must be vertical to the upper surface of the foundation (measured and tested with an angle ruler);

3. Place the pit for 1-2 days after excavation to see if there is groundwater seepage. Stop construction immediately if groundwater seeps out;

4. Before construction, prepare the tools required for making the solar street lamp foundation and select the construction personnel with construction experience;

5. The proper cement shall be selected in strict accordance with the foundation map of solar street lamps, and the special cement resistant to acid and alkali must be selected in the places with high soil acidity and alkalinity; The fine sand and stone shall be free of impurities that affect the concrete strength, such as soil;

6. The soil around the foundation must be compacted;

7. Drain holes must be added to the bottom of the tank where the battery compartment is placed in the foundation according to the drawing requirements;

8. Before construction, both ends of the threading pipe must be blocked to prevent foreign matters from entering or blocking during or after construction, which may lead to difficult threading or failure to threading during installation;

9. The foundation of solar street lamp shall be maintained for 5 to 7 days after completion of fabrication (determined according to weather conditions);

foundation

10. The installation of solar street lamps can only be carried out after the foundation of solar street lamps is accepted as qualified.

The above precautions for installing the foundation of solar street lamps are shared here. Due to the different heights of various solar street lamps and the size of the wind force, the foundation strength of various solar street lamps is different. During construction, it is necessary to ensure that the foundation strength and structure meet the design requirements.


Post time: Nov-18-2022